UK pushes Navantia to accelerate delivery of Royal Navy support ships

The UK Ministry of Defence is pushing Navantia for earlier delivery of three Fleet Solid Support ships as construction of the first vessel advances at Appledore.

Three Fleet Solid Support vessels being delivered for the Royal Fleet Auxiliary through a partnership between Navantia UK, BMT and Harland & Wolff.
Photo: Navantia

The Ministry of Defence is pressing Navantia to accelerate delivery of three new Fleet Solid Support ships as UK seeks to strengthen the Royal Navy’s ability to sustain its carrier strike force at sea.

Navantia UK chief executive Donato Martinez confirmed that the MoD wants the vessels earlier than the existing schedule, under which the first ship is expected to go to sea from 2030 and all three are due to be completed by 2032, The Times first reported on Monday.

Three Fleet Solid Support vessels being delivered for the Royal Fleet Auxiliary through a partnership between Navantia UK, BMT and Harland & Wolff.
Photo: Navantia

“We have a target date. But the Ministry of Defence is pursuing a quicker delivery date,” Martinez told the newspaper. “The customer is pushing. It makes it more challenging but we are trying.”

The pressure comes as construction reaches another milestone. The keel of the first ship is due to be laid at Navantia UK’s Appledore yard in Devon on 2 September, formally marking the start of construction there after a six-year gap in shipbuilding at the site.

Three large ships will sustain the Royal Navy’s carrier force far from port

The Fleet Solid Support programme will provide three ships for the Royal Fleet Auxiliary, which supplies Royal Navy warships while deployed.

Navantia UK team briefing Rear Admiral Matthew Stratton on the Fleet Solid Support shipbow construction and Harland & Wolff integration plans inside the Appledore shipyard.
Photo: Navantia

The vessels are designed principally to support the UK’s Carrier Strike Group, transferring ammunition, spare parts, food and other stores at sea. That allows the force to remain deployed for longer without returning to port for replenishment.

Each ship will be 216 metres long and displace more than 39,000 tonnes. That will make them the second-largest ships serving with the UK military after the Royal Navy’s Queen Elizabeth-class aircraft carriers.

The £1.6 billion manufacturing contract was awarded to Team Resolute in January 2023, with Navantia UK as prime contractor alongside Harland & Wolff and naval architecture company BMT.

The Times describes the wider programme as a £2 billion contract. Navantia’s original contract announcement, however, puts the manufacturing contract at £1.6 billion.

The requirement itself is much older. The UK identified the need for new support ships in its 2015 Strategic Defence and Security Review, meaning Wednesday’s keel-laying comes 11 years after the requirement was formally recognised.

Construction is spread between Appledore, Belfast and Spain

Work on the first vessel, RFA Resurgent, is already under way. First steel was cut at Appledore in December 2025, while construction of modules at Navantia’s facilities in Cádiz began subsequently.

The programme uses several yards. Appledore will construct the ships’ bow sections, while modules built in Spain will be transferred to Belfast, where final integration will take place.

That industrial arrangement has become more complicated since the contract was awarded. Harland & Wolff entered administration before Navantia acquired the business and its four UK shipyards in early 2025, taking control of Belfast and Appledore and responsibility for delivering the FSS programme.

Navantia UK marks its first year of owning Harland & Wolff, highlighting progress across its four sites
Photo: Navantia

Accelerating the ships will therefore require Navantia to expand a British shipbuilding workforce that is still being rebuilt. According to The Times, Appledore now has more than 200 workers and is close to full operation. Belfast has around 500 employees but requires another 1,000 before it is ready for final assembly of the support ships.

The challenge is particularly significant in Belfast, which has not built a ship since 2003, while Appledore last delivered a vessel six years ago.

Ageing support fleet adds urgency to delivery timetable

The FSS ships fill an important gap behind Britain’s two aircraft carriers. The Royal Fleet Auxiliary currently has only one solid-support vessel, the 36-year-old RFA Fort Victoria, which The Times reported is out of service undergoing refit.

Without sufficient replenishment ships, the endurance of a carrier strike group is constrained regardless of the capability of the carrier and its escorts. The FSS programme is intended to restore that logistical depth.

Team Resolute—comprising Navantia UK, Harland & Wolff, and BMT—secured a £1.6 billion contract to build three Fleet Solid Support (FSS) ships for the Royal Fleet Auxiliary, with construction spanning Belfast, Appledore, and Cadiz.
Photo: Navantia

The MoD’s push for faster delivery also comes as the government calls for greater military readiness amid worsening security conditions in Europe.

For Navantia, meeting an accelerated timetable could have implications beyond the three ships. Martinez told The Times that the company wants its performance on FSS to become a “differentiator” as it pursues further Royal Navy work.

That includes the planned Type 91 uncrewed weapons vessels, Type 92 submarine-hunting ships and Type 94 surveillance vessels envisaged as part of the Royal Navy’s future hybrid fleet.

Navantia is also interested in the UK’s planned eight new amphibious transport vessels.

Related

RAF Air Command becomes Air and Space Command as Britain elevates military space operations
An RAF-operated Typhoon FGR4 is displayed alongside two Storm Shadow ALCMs during an event at RAF Marham, Norfolk, on 1 September 2019. Image: MOD Crown Copyright/SAC Simon Armstrong
RAF Air Command becomes Air and Space Command as Britain elevates military space operations
With the growing importance of military space operations, the new name reflects the widening remit of the RAF’s primary operational division.
Aerospace Defence

1 Sep 2026

TEKEVER acquires Edinburgh-based Flowcopter
FIA 2026
TEKEVER acquires Edinburgh-based Flowcopter
The move is designed to expand TEKEVER's autonomous capabilities with advanced propulsion technology.
Global aircraft order backlog tops 17,000 for the first time as demand outpaces production
Boeing 737 factory in Renton
Global aircraft order backlog tops 17,000 for the first time as demand outpaces production
New ADS figures show the global commercial aircraft backlog reached a record 17,037 jets in July, with strong airline demand continuing to outstrip manufacturers' delivery capacity.
Aerospace

1 Sep 2026

RAF Air Command becomes Air and Space Command as Britain elevates military space operations
An RAF-operated Typhoon FGR4 is displayed alongside two Storm Shadow ALCMs during an event at RAF Marham, Norfolk, on 1 September 2019. Image: MOD Crown Copyright/SAC Simon Armstrong
RAF Air Command becomes Air and Space Command as Britain elevates military space operations
With the growing importance of military space operations, the new name reflects the widening remit of the RAF’s primary operational division.
Aerospace Defence

1 Sep 2026

TEKEVER acquires Edinburgh-based Flowcopter
FIA 2026
TEKEVER acquires Edinburgh-based Flowcopter
The move is designed to expand TEKEVER's autonomous capabilities with advanced propulsion technology.
Royal Navy monitors Russian warships and shadow fleet activity as UK surveillance rises 25%
HMS St Albans monitoring Admiral Levchenko
Royal Navy monitors Russian warships and shadow fleet activity as UK surveillance rises 25%
Three Royal Navy vessels and a Merlin helicopter tracked Russian warships and sanctioned cargo ships through the North Sea and English Channel as monitoring activity around UK waters continues to increase.
Defence

1 Sep 2026

Teledyne passes 1,000 sensors in orbit with NASA Roman Telescope launch
The infrared focal plane with H4RG-10 detector
Teledyne passes 1,000 sensors in orbit with NASA Roman Telescope launch
The launch of NASA's Nancy Grace Roman Space Telescope marks a major milestone for Teledyne, whose detector technology will enable the mission to investigate dark energy, hunt for exoplanets and survey billions of galaxies.
Member News Space

1 Sep 2026

ADS cyclists battle crashes, climbs and forest fires to raise over £5,000
ADS Charity Cycle
ADS cyclists battle crashes, climbs and forest fires to raise over £5,000
Industry riders covered 334 miles from Belfast to Bristol in support of Combat Stress, O2e and Air Ambulance Northern Ireland.
Scottish space tech to power self-consuming rocket engine
Alpha Impulsion
Scottish space tech to power self-consuming rocket engine
Aurora Avionics is to supply crucial electronic systems that will deliver key electrical power functions for a pioneering new rocket engine, that aims to cut propulsion costs and support next-generation spacecraft.
Space

27 Aug 2026

TEKEVER acquires Edinburgh-based Flowcopter
FIA 2026
TEKEVER acquires Edinburgh-based Flowcopter
The move is designed to expand TEKEVER's autonomous capabilities with advanced propulsion technology.
Metropolitan Police Force expands its fleet of crime-fighting e-bikes
Met Sur-Ron eBikes at New Scotland Yard
Metropolitan Police Force expands its fleet of crime-fighting e-bikes
As it continues to address the challenge posed by criminals using e-bikes and mopeds to commit crime and evade the law, the Metropolitan Police Force has substantially increased its own fleet of Sur-Ron e-bikes, to tackle the perpetrators.
Security

31 Aug 2026

ADS cyclists battle crashes, climbs and forest fires to raise over £5,000
ADS Charity Cycle
ADS cyclists battle crashes, climbs and forest fires to raise over £5,000
Industry riders covered 334 miles from Belfast to Bristol in support of Combat Stress, O2e and Air Ambulance Northern Ireland.