Aircraft return to RAF Brize Norton after runway reopened

Aircraft have returned to RAF Brize Norton following a full replacement of the Station’s three kilometre (1.86 miles) runway in just 16 weeks.

RAF Brize Norton runway
Photo: DIO / MoD Crown Copyright

Aircraft have returned to RAF Brize Norton following a full replacement of the Station’s three kilometre (1.86 miles) runway in just 16 weeks.

The Defence Infrastructure Organisation (DIO) handed the runway back to Air Commodore Phil Reid, Head of Air Infrastructure, on behalf of the RAF, marking a major milestone in a wider £180 million project to overhaul critical airfield infrastructure at the Station. Working with Air Infrastructure, DIO appointed VolkerFitzpatrick to deliver the works, with AECOM providing technical services throughout the project.

Air Commodore Phil Reid, Head of Air Infrastructure, said: “This success has only been achieved with tremendous team effort, which will continue through to overall project completion late in 2027. This specific work at RAF Brize Norton will strengthen the airfield’s long-term strategic and operational capabilities, safety and resilience.”

The new runway has been constructed using Pavement Quality Concrete (PQC) and Grooved Marshall Asphalt, which have been selected to improve the runway’s resilience to higher temperatures and the effects of climate change. The use of PQC is expected to more than double the runway’s service life compared with the materials previously used, ensuring the base can remain fully operational and fit for decades to come while delivering long-term value for money.

Aircraft were dispersed to several alternative locations during the 16-week construction period, enabling operations to continue while the runway was replaced.

Aircraft lands at RAF Brize Norton
Photo: DIO / MoD Crown Copyright


The first aircraft touched down on the new runway on Friday 13 November.

Strengthening RAF Brize Norton’s future operational capability

Mike Green, Chief Executive of DIO and DG Infrastructure for the National Armaments Director Group, said: “This has been a tremendous team effort. Delivering at pace while maintaining our focus on the RAF’s operational needs is no small achievement. The collaboration between DIO, the RAF and our contractors has been outstanding, and the result speaks for itself.”

The new runway will ensure the Station remains fully operational and fit for decades to come

Bob Noyes, DIO Principal Project Manager, said: “After an incredibly busy 16 weeks, it is fantastic to see aircraft returning home to RAF Brize Norton and using the new runway. I am proud of the immense teamwork that has gone into delivering this major element of the programme in such a short period, supporting the Station’s vital role in military operations around the world.”

The runway replacement forms part of a wider programme that includes the refurbishment of taxiways and associated infrastructure, upgrades to airfield lighting systems and improvements to drainage and supporting infrastructure. This work will strengthen the airfield’s long-term operational capability, safety and resilience.

The programme is funded through the Defence Investment Plan, which includes investment into the refurbishment of major runways and renewal of the critical infrastructure across the Defence estate.

Related

First UK-built Islander from revived Isle of Wight production line delivered to Falklands
FIGAS Britten-Norman Islander
First UK-built Islander from revived Isle of Wight production line delivered to Falklands
Britten-Norman has delivered the first Islander aircraft built on its revived Isle of Wight production line to the Falkland Islands Government Air Service following a three-week ferry flight.
Aerospace

20 Nov 2026

Viasat launches VIA to work across all in-flight connectivity networks
Viasat launches VIA to work across all in-flight connectivity networks
A cloud-delivered media platform that runs on any in-flight connectivity network - including via satellite - has been launched by Viasat, which can enable airlines to deliver their own branded experience across their fleets.
Rolls-Royce secures Royal Brunei Trent 1000 XE order for Boeing 787-9s
Rolls Royce Trent 1000
Rolls-Royce secures Royal Brunei Trent 1000 XE order for Boeing 787-9s
Rolls-Royce will supply eight new Trent 1000 XE engines for four Boeing 787-9 Dreamliners for Royal Brunei Airlines.
Aerospace

20 Nov 2026

Kromek receives £2.5m radiation detectors order from MoD
Arnab Basu, CEO of Kromek
Kromek receives £2.5m radiation detectors order from MoD
The UK Ministry of Defence has placed a second order with Kromek for its wearable D5 RIID radiation detection device, valued at £2.5 million.
Defence Member News

20 Nov 2026

UK conducting offensive cyber operations as it counters threats from Russia, China, Iran and North Korea
close up of someone programming computers
UK conducting offensive cyber operations as it counters threats from Russia, China, Iran and North Korea
Britain is conducting offensive cyber operations against hostile states, with a senior military commander warning the UK is neither at war nor fully at peace.
Defence

20 Nov 2026

Cirrus aircraft mistaken for drones near RAF Lakenheath and in Moldova
Cirrus SR20 on the ground
Cirrus aircraft mistaken for drones near RAF Lakenheath and in Moldova
A trio of Cirrus SR20 light aircraft appear to have triggered drone warnings twice on their journey from the US to India, highlighting the high rate of false alarms.
Defence

20 Nov 2026

Viasat launches VIA to work across all in-flight connectivity networks
Viasat launches VIA to work across all in-flight connectivity networks
A cloud-delivered media platform that runs on any in-flight connectivity network - including via satellite - has been launched by Viasat, which can enable airlines to deliver their own branded experience across their fleets.
Hexagon and Red Bull look beyond engineering degrees to find manufacturing’s future talent
Formula 1 car at Red Bull's MK7 campus
Hexagon and Red Bull look beyond engineering degrees to find manufacturing’s future talent
At Red Bull’s Milton Keynes campus, Hexagon brought students and employers together to explore how interests in gaming, data and problem-solving could become a route into manufacturing — and what industry needs to do to open those doors.
University of Surrey develops electronic eye to monitor solar storms
HEPI prototype ‘electronic eye’ sensor
University of Surrey develops electronic eye to monitor solar storms
Under a £400,000 contract with the European Space Agency (ESA) and the UK Space Agency (UKSA), a team of researchers at the University of Surrey will develop an ultra-compact monitor to reveal the effects of radiation from solar storms on space infrastructure, aircraft and terrestrial systems like satellites.
Aerospace Space

18 Nov 2026

Met launches handheld facial recognition pilot for frontline identity checks
New Scotland Yard sign
Met launches handheld facial recognition pilot for frontline identity checks
The Metropolitan Police have launched a six-month trial of a new handheld facial recognition tool that allows officers to verify a person's identity without their consent by comparing a photograph taken on a police-issued mobile device against the force's custody image database.
Security

20 Nov 2026

Hexagon and Red Bull look beyond engineering degrees to find manufacturing’s future talent
Formula 1 car at Red Bull's MK7 campus
Hexagon and Red Bull look beyond engineering degrees to find manufacturing’s future talent
At Red Bull’s Milton Keynes campus, Hexagon brought students and employers together to explore how interests in gaming, data and problem-solving could become a route into manufacturing — and what industry needs to do to open those doors.
Expert shares what SMEs should do in the first two hours of an energy or cyber disruption
Server racks creating data center corridor 3d
Expert shares what SMEs should do in the first two hours of an energy or cyber disruption
Cyber attacks, grid failures and rising electricity demand are creating new business risks. Dr Phil Wu explains the three actions SMEs should take in the first two hours of a disruption.
Security

19 Nov 2026