Advancing UK Aerospace, Defence, Security & Space Solutions Worldwide
  • Home
  • /
  • Defence
  • /
  • NAO report identifies MoD defence capabilities delivery challenges

Defence

NAO report identifies MoD defence capabilities delivery challenges

The Ministry of Defence (MoD) is struggling to deliver key parts of the UK’s planned defence capabilities programme, according to a recently published National Audit Office (NAO) report, Defence capabilities – delivering what was promised.


Image copyright Shutterstock

New military capabilities – the combination of equipment, trained personnel, infrastructure and information needed to meet a specific requirement of the Armed Forces – are pivotal to delivering the UK’s defence policy.

These capabilities cover major projects such as offshore patrol vessels, fighter aircraft, drones and battlefield communication systems. The estimated total procurement cost of the 32 most significant defence projects and programmes is £196.2 billion. To deliver such capabilities, the MoD employs around 20,000 staff.

Advertisement
ODU RT

The NAO finds that projects are not being consistently delivered to the expected standard or on time. At a time of fast-paced technological developments and global change, it is essential that the MoD can make swift and full use of the capabilities it needs as planned. Failure to deliver them on time is likely to undermine the MoD’s ability to carry out its key tasks, and lead to overextended use of existing assets, and additional costs.

Gareth Davies, head of the NAO, said: “It is essential that the MoD improves the way it introduces important new defence capabilities into service. This includes ensuring that pressure to be seen to deliver quickly does not lead to it accepting incomplete projects, and making decisions on the basis of incomplete reporting.”

Ten of the MoD’s 32 most significant projects and programmes either require urgent action to get back on track, or already cannot be delivered on time. Whereas, five of the 32 are currently likely to be delivered on schedule. These projects and programmes are forecast to be on average more than two years late by the time they are declared as fully operational.

A persistent ongoing problem the MoD faces is equipment delivered either late or faulty by its suppliers. Nearly a third of the 32 most significant projects report serious issues with suppliers. In some cases, poor performance has persisted over a number of years.

MoD project and delivery teams are under-resourced and lack essential skills, contributing to delays in delivery. Six of the 32 projects face shortfalls of more than 20% in their programme teams. The report also highlights shortages of key staff and how some teams are reliant on consultancy support. The MoD also does not have the information it needs to hold teams to account and make strategic decisions.

Advertisement
ODU RT

The NAO has also identified examples where poorly defined delivery ‘milestones’ have meant the MoD has been unclear what has actually been achieved. Projects can be declared ‘fully operational’ even if they are not or if testing is incomplete. In some cases, this has affected MoD’s ability to use equipment in the way intended.

In response to these challenges, the MoD is introducing a new approach to procurement, designed to speed up delivery, and allow it to flexibly upgrade equipment in response to technological change. For this to successfully tackle the issues highlighted in the report, the NAO emphasises that key decision makers must have an accurate and current understanding of the level of capability that has been delivered.


 

Advertisement
FIA2026 animated banner
Milanion and RPAL expand Indonesian Navy USV programme

Defence Events

Milanion and RPAL expand Indonesian Navy USV programme

19 June 2026

At Eurosatory 2026 in Paris this week, Milanion Group and PT Republik Palindo Internasional (RPAL) agreed a significant expansion of their unmanned surface vessel (USV) programme for the Indonesian Navy, signing a new collaboration agreement that builds on a live contract already in implementation.

ADS appoints Matthew Reynolds as CIO

Aerospace Defence Security Space Events

ADS appoints Matthew Reynolds as CIO

19 June 2026

ADS Group - parent organisation of trade association ADS and Farnborough International - has appointed Matthew Reynolds as its Chief Information Officer (CIO).

Leonardo awarded critical aircraft spares NAD contract

Defence

Leonardo awarded critical aircraft spares NAD contract

19 June 2026

The National Armaments Director (NAD) Group has awarded a £27 million contract to Leonardo (UK) Ltd to supply critical aircraft consumable spares across the UK’s entire fixed-wing and rotary-wing fleet.

New training targets installed at Holbeach

Defence

New training targets installed at Holbeach

18 June 2026

Two new repurposed marine vessel targets have been successfully delivered and installed at Holbeach Air Weapons Range (AWR), to enhance Defence training.

Advertisement
ODU RT
Serco and StaplesVR partner on immersive training for NZDF

Defence

Serco and StaplesVR partner on immersive training for NZDF

18 June 2026

Serco New Zealand recently formalised a Memorandum of Understanding (MoU) with StaplesVR, bringing together immersive technology and operational training expertise to support the future training capabilities of the New Zealand Defence Force (NZDF).

BAE Systems awarded US Army M109A7 Paladin contract

Defence

BAE Systems awarded US Army M109A7 Paladin contract

17 June 2026

BAE Systems has received a contract award valued at $535 million to produce additional M109A7 Paladin Self-Propelled Howitzers and M992A3 Ammunition Carriers for the US Army.

Advertisement
ODU RT
Advertisement
General Atomics LB