Advancing UK Aerospace, Defence, Security & Space Solutions Worldwide
  • Home
  • /
  • Defence
  • /
  • NAO report identifies MoD defence capabilities delivery challenges

Defence

NAO report identifies MoD defence capabilities delivery challenges

The Ministry of Defence (MoD) is struggling to deliver key parts of the UK’s planned defence capabilities programme, according to a recently published National Audit Office (NAO) report, Defence capabilities – delivering what was promised.


Image copyright Shutterstock

New military capabilities – the combination of equipment, trained personnel, infrastructure and information needed to meet a specific requirement of the Armed Forces – are pivotal to delivering the UK’s defence policy.

These capabilities cover major projects such as offshore patrol vessels, fighter aircraft, drones and battlefield communication systems. The estimated total procurement cost of the 32 most significant defence projects and programmes is £196.2 billion. To deliver such capabilities, the MoD employs around 20,000 staff.

Advertisement
ODU RT

The NAO finds that projects are not being consistently delivered to the expected standard or on time. At a time of fast-paced technological developments and global change, it is essential that the MoD can make swift and full use of the capabilities it needs as planned. Failure to deliver them on time is likely to undermine the MoD’s ability to carry out its key tasks, and lead to overextended use of existing assets, and additional costs.

Gareth Davies, head of the NAO, said: “It is essential that the MoD improves the way it introduces important new defence capabilities into service. This includes ensuring that pressure to be seen to deliver quickly does not lead to it accepting incomplete projects, and making decisions on the basis of incomplete reporting.”

Ten of the MoD’s 32 most significant projects and programmes either require urgent action to get back on track, or already cannot be delivered on time. Whereas, five of the 32 are currently likely to be delivered on schedule. These projects and programmes are forecast to be on average more than two years late by the time they are declared as fully operational.

A persistent ongoing problem the MoD faces is equipment delivered either late or faulty by its suppliers. Nearly a third of the 32 most significant projects report serious issues with suppliers. In some cases, poor performance has persisted over a number of years.

MoD project and delivery teams are under-resourced and lack essential skills, contributing to delays in delivery. Six of the 32 projects face shortfalls of more than 20% in their programme teams. The report also highlights shortages of key staff and how some teams are reliant on consultancy support. The MoD also does not have the information it needs to hold teams to account and make strategic decisions.

Advertisement
ODU RT

The NAO has also identified examples where poorly defined delivery ‘milestones’ have meant the MoD has been unclear what has actually been achieved. Projects can be declared ‘fully operational’ even if they are not or if testing is incomplete. In some cases, this has affected MoD’s ability to use equipment in the way intended.

In response to these challenges, the MoD is introducing a new approach to procurement, designed to speed up delivery, and allow it to flexibly upgrade equipment in response to technological change. For this to successfully tackle the issues highlighted in the report, the NAO emphasises that key decision makers must have an accurate and current understanding of the level of capability that has been delivered.


 

Advertisement
FIA2026 animated banner
Accles & Pollock expands its capabilities

Aerospace Defence

Accles & Pollock expands its capabilities

16 June 2026

West Midlands based Accles & Pollock – a trading division of Clydesdale Engineering Ltd – is further expanding its capabilities to include presswork, laser cutting and metal fabrication.

NP Aerospace receives GDLS add-on armour contract

Defence

NP Aerospace receives GDLS add-on armour contract

16 June 2026

NP Aerospace has today announced the award of a contract by General Dynamics Land Systems–Canada (GDLS–Canada) for the design and manufacture of add-on vehicle armour systems for a Light Armoured Vehicle (LAV) international order.

Avon Protection introduces short-duration CBRN CS-PAPR

Defence Security Events

Avon Protection introduces short-duration CBRN CS-PAPR

16 June 2026

Avon Protection has introduced its Combination System Powered Air Purifying Respirator (CS-PAPR), a new short duration (SD) breathing apparatus option of their Powered Air Purifying Respirator (PAPR) for integration with a Combination Respirator Unit (CRU).

Thales unveils LGR275 Proxy at Eurosatory

Defence Events

Thales unveils LGR275 Proxy at Eurosatory

16 June 2026

Thales has unveiled its LGR275 Proxy at Eurosatory in Paris, a 70mm laser-guided rocket specifically designed to effectively neutralise the threat posed by Unmanned Aerial Systems (UAS).

Advertisement
ODU RT
Clarion appoints James Samuel as Managing Director – Live Events

Defence Events

Clarion appoints James Samuel as Managing Director – Live Events

16 June 2026

Clarion Events Defence and Security has appointed James Samuel as its new Managing Director – Live Events, to lead DSEI’s global expansion.

Roke launches Nav-Sync Armour

Defence

Roke launches Nav-Sync Armour

16 June 2026

Romsey based Roke has launched Nav-Sync Armour, a Controlled Reception Pattern Antenna (CRPA) system redefining access to resilient navigation across globally contested environments.

Advertisement
ODU RT
Advertisement
General Atomics LB