Advancing UK Aerospace, Defence, Security & Space Solutions Worldwide
  • Home
  • /
  • Defence
  • /
  • NAO report identifies MoD defence capabilities delivery challenges

Defence

NAO report identifies MoD defence capabilities delivery challenges

The Ministry of Defence (MoD) is struggling to deliver key parts of the UK’s planned defence capabilities programme, according to a recently published National Audit Office (NAO) report, Defence capabilities – delivering what was promised.


Image copyright Shutterstock

New military capabilities – the combination of equipment, trained personnel, infrastructure and information needed to meet a specific requirement of the Armed Forces – are pivotal to delivering the UK’s defence policy.

These capabilities cover major projects such as offshore patrol vessels, fighter aircraft, drones and battlefield communication systems. The estimated total procurement cost of the 32 most significant defence projects and programmes is £196.2 billion. To deliver such capabilities, the MoD employs around 20,000 staff.

Advertisement
ODU RT

The NAO finds that projects are not being consistently delivered to the expected standard or on time. At a time of fast-paced technological developments and global change, it is essential that the MoD can make swift and full use of the capabilities it needs as planned. Failure to deliver them on time is likely to undermine the MoD’s ability to carry out its key tasks, and lead to overextended use of existing assets, and additional costs.

Gareth Davies, head of the NAO, said: “It is essential that the MoD improves the way it introduces important new defence capabilities into service. This includes ensuring that pressure to be seen to deliver quickly does not lead to it accepting incomplete projects, and making decisions on the basis of incomplete reporting.”

Ten of the MoD’s 32 most significant projects and programmes either require urgent action to get back on track, or already cannot be delivered on time. Whereas, five of the 32 are currently likely to be delivered on schedule. These projects and programmes are forecast to be on average more than two years late by the time they are declared as fully operational.

A persistent ongoing problem the MoD faces is equipment delivered either late or faulty by its suppliers. Nearly a third of the 32 most significant projects report serious issues with suppliers. In some cases, poor performance has persisted over a number of years.

MoD project and delivery teams are under-resourced and lack essential skills, contributing to delays in delivery. Six of the 32 projects face shortfalls of more than 20% in their programme teams. The report also highlights shortages of key staff and how some teams are reliant on consultancy support. The MoD also does not have the information it needs to hold teams to account and make strategic decisions.

Advertisement
ODU RT

The NAO has also identified examples where poorly defined delivery ‘milestones’ have meant the MoD has been unclear what has actually been achieved. Projects can be declared ‘fully operational’ even if they are not or if testing is incomplete. In some cases, this has affected MoD’s ability to use equipment in the way intended.

In response to these challenges, the MoD is introducing a new approach to procurement, designed to speed up delivery, and allow it to flexibly upgrade equipment in response to technological change. For this to successfully tackle the issues highlighted in the report, the NAO emphasises that key decision makers must have an accurate and current understanding of the level of capability that has been delivered.


 

Advertisement
Gulfstream banner
Roke introduces CORTEXA GUARDIAN

Defence Events

Roke introduces CORTEXA GUARDIAN

21 April 2026

Roke has introduced its new, advanced Counter UAS (C-UAS), CORTEXA GUARDIAN to the market, following the system's development with armed forces and mission partners across the UK and Northern Europe.

Anotec achieves AS9100 certification

Aerospace Defence

Anotec achieves AS9100 certification

20 April 2026

Surface coating specialist Anotec has enhanced its position in the aerospace and defence sectors by achieving the AS9100 certification.

Securitas appoints Alan Rae as Area Director for UK North and BAE Systems

Defence Security

Securitas appoints Alan Rae as Area Director for UK North and BAE Systems

20 April 2026

Securitas UK has announced the appointment of Alan Rae to the newly created and expanded role of Area Director for UK North and BAE Systems.

Vision Engineering appoints Harry Curtis as Technical Director

Aerospace Defence

Vision Engineering appoints Harry Curtis as Technical Director

17 April 2026

Woking headquartered Vision Engineering Group, provider of ergonomic microscopy and metrology solutions, has announced the appointment of Harry Curtis to the position of Technical Director, effective 1st April 2026.

Advertisement
ODU RT
Drone swarms central to AWE26

Defence Events

Drone swarms central to AWE26

17 April 2026

Drones have been at the centre of this year's Army Warfighting Experiment 2026, which each year brings together soldiers, scientists, industry and universities, to test new military technology.

Dstl assesses robotic systems in hazardous incident recovery trial

Defence

Dstl assesses robotic systems in hazardous incident recovery trial

17 April 2026

In a ‘real life’ scenario played out in an empty shopping unit, the Defence Science and Technology Laboratory (Dstl) has tested the ability of robotic and autonomous systems to navigate through a building and detect, sample and remediate (clean) a contaminated environment.

Advertisement
ODU RT
Advertisement
Gulfstream banner