Advancing UK Aerospace, Defence, Security & Space Solutions Worldwide
  • Home
  • /
  • Defence
  • /
  • NAO report identifies MoD defence capabilities delivery challenges

Defence

NAO report identifies MoD defence capabilities delivery challenges

The Ministry of Defence (MoD) is struggling to deliver key parts of the UK’s planned defence capabilities programme, according to a recently published National Audit Office (NAO) report, Defence capabilities – delivering what was promised.


Image copyright Shutterstock

New military capabilities – the combination of equipment, trained personnel, infrastructure and information needed to meet a specific requirement of the Armed Forces – are pivotal to delivering the UK’s defence policy.

These capabilities cover major projects such as offshore patrol vessels, fighter aircraft, drones and battlefield communication systems. The estimated total procurement cost of the 32 most significant defence projects and programmes is £196.2 billion. To deliver such capabilities, the MoD employs around 20,000 staff.

Advertisement
Leonardo animated rectangle

The NAO finds that projects are not being consistently delivered to the expected standard or on time. At a time of fast-paced technological developments and global change, it is essential that the MoD can make swift and full use of the capabilities it needs as planned. Failure to deliver them on time is likely to undermine the MoD’s ability to carry out its key tasks, and lead to overextended use of existing assets, and additional costs.

Gareth Davies, head of the NAO, said: “It is essential that the MoD improves the way it introduces important new defence capabilities into service. This includes ensuring that pressure to be seen to deliver quickly does not lead to it accepting incomplete projects, and making decisions on the basis of incomplete reporting.”

Ten of the MoD’s 32 most significant projects and programmes either require urgent action to get back on track, or already cannot be delivered on time. Whereas, five of the 32 are currently likely to be delivered on schedule. These projects and programmes are forecast to be on average more than two years late by the time they are declared as fully operational.

A persistent ongoing problem the MoD faces is equipment delivered either late or faulty by its suppliers. Nearly a third of the 32 most significant projects report serious issues with suppliers. In some cases, poor performance has persisted over a number of years.

MoD project and delivery teams are under-resourced and lack essential skills, contributing to delays in delivery. Six of the 32 projects face shortfalls of more than 20% in their programme teams. The report also highlights shortages of key staff and how some teams are reliant on consultancy support. The MoD also does not have the information it needs to hold teams to account and make strategic decisions.

Advertisement
ODU RT

The NAO has also identified examples where poorly defined delivery ‘milestones’ have meant the MoD has been unclear what has actually been achieved. Projects can be declared ‘fully operational’ even if they are not or if testing is incomplete. In some cases, this has affected MoD’s ability to use equipment in the way intended.

In response to these challenges, the MoD is introducing a new approach to procurement, designed to speed up delivery, and allow it to flexibly upgrade equipment in response to technological change. For this to successfully tackle the issues highlighted in the report, the NAO emphasises that key decision makers must have an accurate and current understanding of the level of capability that has been delivered.


 

Advertisement
General Atomics LB
Aldershot and Farnborough to host 2026 National Armed Forces Day

Defence Events

Aldershot and Farnborough to host 2026 National Armed Forces Day

5 December 2025

Rushmoor borough has today been awarded the prestigious honour of hosting the 2026 National Armed Forces Day celebrations.

Blighter adds radar target tracker to BlighterNexus system

Defence Security

Blighter adds radar target tracker to BlighterNexus system

5 December 2025

Cambridge based Blighter has added a proprietary dynamic radar target tracker module to its integrator-friendly BlighterNexus AI-assisted multisensor connectivity & processing system.

Serco to support RCAF FAcT

Defence

Serco to support RCAF FAcT

5 December 2025

Serco has been awarded a 25-year contract by SkyAlyne to support its Future Aircrew Training (FAcT) programme for the Royal Canadian Air Force (RCAF).

Babcock strengthens French defence training with L-39

Defence

Babcock strengthens French defence training with L-39

4 December 2025

Babcock France has been awarded a contract to support the French Test Pilot school (EPNER) with an L-39 aircraft – the first for its fleet.

Advertisement
Tritax 300x250
Navantia UK hosts official FSS steel cutting ceremony in Appledore

Defence

Navantia UK hosts official FSS steel cutting ceremony in Appledore

4 December 2025

The traditional steel cutting ceremony was held at Navantia UK’s Appledore shipyard in North Devon yesterday, marking a significant achievement for the FSS programme that is driving a £100 million investment across Belfast and Appledore.

British designed satellites successfully launched

Defence Security Space

British designed satellites successfully launched

3 December 2025

A cluster of British designed and built satellites has been successfully launched into low Earth orbit, providing defence, security and civil sectors with UK space-based intelligence, surveillance and reconnaissance to enhance the nation’s ability to protect against modern threats.

Advertisement
Tritax 300x250