Advancing UK Aerospace, Defence, Security & Space Solutions Worldwide
  • Home
  • /
  • Defence
  • /
  • NAO report identifies MoD defence capabilities delivery challenges

Defence

NAO report identifies MoD defence capabilities delivery challenges

The Ministry of Defence (MoD) is struggling to deliver key parts of the UK’s planned defence capabilities programme, according to a recently published National Audit Office (NAO) report, Defence capabilities – delivering what was promised.


Image copyright Shutterstock

New military capabilities – the combination of equipment, trained personnel, infrastructure and information needed to meet a specific requirement of the Armed Forces – are pivotal to delivering the UK’s defence policy.

These capabilities cover major projects such as offshore patrol vessels, fighter aircraft, drones and battlefield communication systems. The estimated total procurement cost of the 32 most significant defence projects and programmes is £196.2 billion. To deliver such capabilities, the MoD employs around 20,000 staff.

Advertisement
Tritax 300x250

The NAO finds that projects are not being consistently delivered to the expected standard or on time. At a time of fast-paced technological developments and global change, it is essential that the MoD can make swift and full use of the capabilities it needs as planned. Failure to deliver them on time is likely to undermine the MoD’s ability to carry out its key tasks, and lead to overextended use of existing assets, and additional costs.

Gareth Davies, head of the NAO, said: “It is essential that the MoD improves the way it introduces important new defence capabilities into service. This includes ensuring that pressure to be seen to deliver quickly does not lead to it accepting incomplete projects, and making decisions on the basis of incomplete reporting.”

Ten of the MoD’s 32 most significant projects and programmes either require urgent action to get back on track, or already cannot be delivered on time. Whereas, five of the 32 are currently likely to be delivered on schedule. These projects and programmes are forecast to be on average more than two years late by the time they are declared as fully operational.

A persistent ongoing problem the MoD faces is equipment delivered either late or faulty by its suppliers. Nearly a third of the 32 most significant projects report serious issues with suppliers. In some cases, poor performance has persisted over a number of years.

MoD project and delivery teams are under-resourced and lack essential skills, contributing to delays in delivery. Six of the 32 projects face shortfalls of more than 20% in their programme teams. The report also highlights shortages of key staff and how some teams are reliant on consultancy support. The MoD also does not have the information it needs to hold teams to account and make strategic decisions.

Advertisement
ODU RT

The NAO has also identified examples where poorly defined delivery ‘milestones’ have meant the MoD has been unclear what has actually been achieved. Projects can be declared ‘fully operational’ even if they are not or if testing is incomplete. In some cases, this has affected MoD’s ability to use equipment in the way intended.

In response to these challenges, the MoD is introducing a new approach to procurement, designed to speed up delivery, and allow it to flexibly upgrade equipment in response to technological change. For this to successfully tackle the issues highlighted in the report, the NAO emphasises that key decision makers must have an accurate and current understanding of the level of capability that has been delivered.


 

Advertisement
Cranfield University
Morphose Capital Partners appoints Andre Turville as CEO

Aerospace Defence Security

Morphose Capital Partners appoints Andre Turville as CEO

14 November 2025

Morphose Capital Partners has formally welcomed Andre Turville as its new Chief Executive Officer (CEO).

FSS completes CDR

Defence

FSS completes CDR

13 November 2025

The Royal Fleet Auxiliary (RFA) is a step closer to receiving highly capable new support ships following successful completion of the Fleet Solid Support (FSS) programme's Critical Design Review (CDR).

Leonardo selects Unison CNC tube bender for Merlin maintenance

Defence

Leonardo selects Unison CNC tube bender for Merlin maintenance

13 November 2025

A manually operated, CNC-controlled tube bending machine from Unison Ltd, is all set to assist Leonardo in ensuring the operational readiness of the AW101 Merlin helicopters based at RNAS Culdrose in Cornwall.

Chess Dynamics

Defence

Chess Dynamics' Omega enters operations with Mellori

13 November 2025

Chess Dynamics has confirmed that its latest high-performance positioner, Omega, is now in operational use as part of Mellori's Blue Jay Horizon system which was launched at the Indo Pacific International Maritime Exposition in Sydney.

Advertisement
Security & Policing Rectangle
Elbit Systems UK delivers GBSR to British Army

Defence

Elbit Systems UK delivers GBSR to British Army

13 November 2025

Bristol based defence technology company, Elbit Systems UK (ESUK), has delivered the first Ground Based Surveillance Radar (GBSR) systems to the Royal Artillery following successful live fire trials earlier this year.

Renishaw’s AM systems integrated into Dassault Systèmes’ 3DEXPERIENCE

Aerospace Defence

Renishaw’s AM systems integrated into Dassault Systèmes’ 3DEXPERIENCE

12 November 2025

Renishaw’s full range of RenAM 500 series of metal additive manufacturing (AM) systems and TEMPUS technology are now integrated into the 3DEXPERIENCE virtual machine from Dassault Systèmes.

Advertisement
Tritax 300x250