Advancing UK Aerospace, Defence, Security & Space Solutions Worldwide
  • Home
  • /
  • Defence
  • /
  • NAO report identifies MoD defence capabilities delivery challenges

Defence

NAO report identifies MoD defence capabilities delivery challenges

The Ministry of Defence (MoD) is struggling to deliver key parts of the UK’s planned defence capabilities programme, according to a recently published National Audit Office (NAO) report, Defence capabilities – delivering what was promised.


Image copyright Shutterstock

New military capabilities – the combination of equipment, trained personnel, infrastructure and information needed to meet a specific requirement of the Armed Forces – are pivotal to delivering the UK’s defence policy.

These capabilities cover major projects such as offshore patrol vessels, fighter aircraft, drones and battlefield communication systems. The estimated total procurement cost of the 32 most significant defence projects and programmes is £196.2 billion. To deliver such capabilities, the MoD employs around 20,000 staff.

Advertisement
ODU RT

The NAO finds that projects are not being consistently delivered to the expected standard or on time. At a time of fast-paced technological developments and global change, it is essential that the MoD can make swift and full use of the capabilities it needs as planned. Failure to deliver them on time is likely to undermine the MoD’s ability to carry out its key tasks, and lead to overextended use of existing assets, and additional costs.

Gareth Davies, head of the NAO, said: “It is essential that the MoD improves the way it introduces important new defence capabilities into service. This includes ensuring that pressure to be seen to deliver quickly does not lead to it accepting incomplete projects, and making decisions on the basis of incomplete reporting.”

Ten of the MoD’s 32 most significant projects and programmes either require urgent action to get back on track, or already cannot be delivered on time. Whereas, five of the 32 are currently likely to be delivered on schedule. These projects and programmes are forecast to be on average more than two years late by the time they are declared as fully operational.

A persistent ongoing problem the MoD faces is equipment delivered either late or faulty by its suppliers. Nearly a third of the 32 most significant projects report serious issues with suppliers. In some cases, poor performance has persisted over a number of years.

MoD project and delivery teams are under-resourced and lack essential skills, contributing to delays in delivery. Six of the 32 projects face shortfalls of more than 20% in their programme teams. The report also highlights shortages of key staff and how some teams are reliant on consultancy support. The MoD also does not have the information it needs to hold teams to account and make strategic decisions.

Advertisement
ODU RT

The NAO has also identified examples where poorly defined delivery ‘milestones’ have meant the MoD has been unclear what has actually been achieved. Projects can be declared ‘fully operational’ even if they are not or if testing is incomplete. In some cases, this has affected MoD’s ability to use equipment in the way intended.

In response to these challenges, the MoD is introducing a new approach to procurement, designed to speed up delivery, and allow it to flexibly upgrade equipment in response to technological change. For this to successfully tackle the issues highlighted in the report, the NAO emphasises that key decision makers must have an accurate and current understanding of the level of capability that has been delivered.


 

Advertisement
General Atomics LB
Marshall Land Systems appoints Jason Beattie as Managing Director - Canada

Defence

Marshall Land Systems appoints Jason Beattie as Managing Director - Canada

29 June 2026

Marshall Land Systems today announced the appointment of Jason Beattie as Managing Director – Canada, effective 13th July 2026.

AtkinsRéalis to support delivery of UK infrastructure

Defence

AtkinsRéalis to support delivery of UK infrastructure

29 June 2026

AtkinsRéalis has been named as a supplier on a major UK government framework to support the design, delivery and optimisation of major infrastructure and building programmes across the built environment, defence and nuclear sectors over the next four years.

Serco named UK’s top employer for Veterans and Reservists

Defence Security

Serco named UK’s top employer for Veterans and Reservists

26 June 2026

Serco has been named the UK’s top employer for veterans, reservists and military families in the 2026 GREAT British Employers of Veterans rankings, highlighting the growing importance of former Armed Forces personnel to the defence support workforce.

Avon Technologies

Defence

Avon Technologies' Team Wendy receives US Army NG IHPS delivery orders

26 June 2026

Avon Technologies have confirmed that Team Wendy Ceradyne has received delivery orders totalling over $40 million from the US Army (ACC) and Defense Logistics Agency (DLA), under the Next Generation Integrated Head Protection System (NG IHPS) helmet contract.

Advertisement
ODU RT
AECOM appoints Andy Thorne as Client Director, Defence, UK & Europe

Defence Security

AECOM appoints Andy Thorne as Client Director, Defence, UK & Europe

26 June 2026

AECOM announced today that it has appointed Andy Thorne as Client Director, Defence, UK & Europe.

QinetiQ facility to enhance UK submarine maintenance

Defence

QinetiQ facility to enhance UK submarine maintenance

25 June 2026

QinetiQ’s additive manufacturing expertise will support the rapid maintenance of the Royal Navy’s submarine fleet through a new onsite facility at HM Naval Base Clyde.

Advertisement
ODU RT
Advertisement
FIA2026 animated banner