Huge section of HMS Queen Elizabeth leaves shipyard

The largest section of future carrier HMS Queen Elizabeth is now complete and on its way to join the rest of the ship.

Above: Employees at BAE Systems' Govan shipyard watch as the aft section of hull makes its way past new destroyer HMS Duncan in the final stages of completion at Scotstoun.
Courtesy BAE Systems 2012

This gigantic segment - officially known as Lower Block 04 and weighing 11,300 tonnes - was towed on a barge down the Clyde on Sunday to begin a 1,230-nautical-mile (2,278km) journey around the south of England to Rosyth.

Advertisement
ODU RT

Originally the shorter route around the north of Scotland had been planned. However, bad weather in the north of the UK forced reconsideration and the route was changed to around the south of England and up to Rosyth through the North Sea.

Employees at BAE Systems' Govan shipyard, where the section was pieced together, and members of the public watched as a large seagoing barge carrying the aft section of hull made its way along the Clyde, past new destroyer HMS Duncan in the final stages of completion at Scotstoun, and under the Erskine Bridge.
 
Travelling around the south coast of England, the block - the final section of the hull to be finished - is scheduled to arrive at Rosyth early next week where it will be joined to the rest of HMS Queen Elizabeth.

Advertisement
Tritax 300x250

Lower Block 04 is 86 metres long, 40 metres wide and 23 metres high and contains the carrier's two main engine rooms, the sick bay and quarters for some of the 1,500 sailors and air group personnel who will serve in her later this decade.
 
Defence Secretary Philip Hammond said: "Our next generation of aircraft carriers is on track, with HMS Queen Elizabeth due to begin sea trials in 2017 and flight trials from her deck using our Lightning II fast jets in 2018. We are regenerating our carrier strike capability with the largest aircraft carriers Britain has ever had and fifth-generation stealth jets.

"Scotland has a world class shipbuilding industry that has benefited to the tune of around £1.3bn from the Queen Elizabeth Class carriers. More than 2,000 people work on the carriers at Rosyth, with a further 2,000 on the Clyde."
 
BAE Systems' Angus Holt, in charge of block delivery for the Queen Elizabeth Class, said: "There's a real sense of pride here in the yard and across the Aircraft Carrier Alliance.
 
"This is the final hull section of HMS Queen Elizabeth and her arrival in Rosyth will mark an exciting and significant phase in the programme when we will really see the immense scale of the nation's flagships."

The giant block was edged out of the firm's shipbuilding hall at Govan a fortnight ago and prepared for its journey by being firmly secured to the seagoing barge. The carrier team closely monitored weather forecasts to plan a smooth journey to the east coast.
 
On its arrival in the Firth of Forth, the block will be floated off the specialist barge and moved into position in dry dock, ready to join the other sections already in place.
 
Around 250 employees from the Clyde will follow the block to Rosyth where they will work in partnership with Babcock to complete the assembly phase.
 
Meanwhile, production on both Lower Blocks 03 and 04 of Queen Elizabeth's sister ship, HMS Prince of Wales, continues to progress at Govan, while the aft island for the first ship is under construction at the company's Scotstoun yard.
 
Half-a-dozen yards around the UK are involved in the carrier project, with some 10,000 people directly or indirectly involved in building sections and parts or providing equipment for the Queen Elizabeth and the Prince of Wales.
 
With the Olympics now over, the construction of the aircraft carriers is the biggest and most complex engineering project in the UK.
 

Advertisement
Cranfield University
BAE Systems to produce additional Bradley A4s for US Army

Defence

BAE Systems to produce additional Bradley A4s for US Army

27 November 2025

The US Army and BAE Systems have definitised a contract modification worth over $390 million to upgrade additional Bradley A4 Fighting Vehicles.

Bourton Group appoints Glenn Gooding as Associate Partner

Aerospace Defence Security

Bourton Group appoints Glenn Gooding as Associate Partner

26 November 2025

Bourton Group LLP has announced the appointment of Glenn Gooding as Associate Partner, to enhance the consultancy’s expertise in supporting UK defence and aerospace manufacturers with operational improvement, engineering excellence and capability development.

Babcock to lead on enhancing Indonesian naval capabilities

Defence Security

Babcock to lead on enhancing Indonesian naval capabilities

26 November 2025

The UK and Indonesia have agreed a landmark £4 billion maritime deal that includes joint development of the Indonesian navy’s maritime capability, with Babcock chosen as the prime industrial partner for the new Maritime Partnership Programme (MPP).

GKN Aerospace and Swedish Defence Ministry to advance UAV demonstrator

Defence

GKN Aerospace and Swedish Defence Ministry to advance UAV demonstrator

26 November 2025

GKN Aerospace has entered into a collaborative programme with the Swedish Defence Materiel Administration (FMV) to develop and demonstrate a flying uncrewed aerial vehicle (UAV) capability within the next 18 months.

Advertisement
ODU RT
Women In Defence UK 10th Anniversary award winners revealed

Defence Events

Women In Defence UK 10th Anniversary award winners revealed

26 November 2025

Women in Defence UK has announced the winners of the 10th Anniversary Women in Defence UK Awards, held yesterday, celebrating a decade of honouring exceptional women, men, individuals and teams who contribute to the defence of the United Kingdom.

BAE Systems awarded US Navy contract for Mk 41 VLS canisters

Defence

BAE Systems awarded US Navy contract for Mk 41 VLS canisters

26 November 2025

BAE Systems has been awarded a $22 million contract by the US Navy to produce missile canisters for the Mk 41 Vertical Launching Systems (VLS), with the total value potentially reaching $317 million.

Advertisement
Tritax 300x250