in Defence

Royal Navy rearming jetty upgraded

Posted 13 January 2022 · Add Comment

The Defence Infrastructure Organisation (DIO) has completed a significant series of upgrades to the Northern Ammunition Jetty at Glen Mallan near Helensburgh.



Above: Aerial image of the Northern Ammunition Jetty at Glen Mallan following completion of the work.
Copyright VolkerStevin 2021


The jetty, which is used to load and unload ammunition for the Royal Navy’s surface fleet, was last upgraded in the 1970s and had reached the end of its economic life. The upgrade work has not only extended the life of the jetty by an estimated fifty years, but has also made the site accessible for the Royal Navy’s aircraft carriers, HMS Queen Elizabeth and HMS Prince of Wales.

The £67-million pounds contract was awarded to VolkerStevin in 2019. Alongside them, DIO also worked with managing agent Jacobs, who provided engineering and professional services, as well as designer Arch Henderson. In completing this major project, £20-million pounds was spent with local suppliers and small and medium enterprises in Scotland.

The previous jetty was demolished and replaced with a new 135m long jetty structure, requiring 127 steel piles to be driven into the loch bed to support a reinforced concrete deck. The works also included the installation of navigation aids and five mooring dolphins which are connected to the jetty by a pedestrian access bridge. Two modular fender spacer units have been placed in front of the new fender panels and move with the tide to prevent the overhanging flight decks of HMS Queen Elizabeth and HMS Prince of Wales from colliding with the jetty.

In addition, the project included the installation of two modern pedestal cranes to load and unload ammunition and the erection of modular buildings for offices, power generation and stores. The perimeter fencing and CCTV system have also been upgraded to provide a complete modern facility.

The team faced a challenge when the scale of HMS Queen Elizabeth’s first planned deployment increased, resulting in the need for the jetty to be operational nine months earlier than originally planned. All parties worked closely together to progress the project sufficiently for the Royal Navy’s flagship to be able to berth at the unfinished jetty, which she did successfully in March this year.

Sustainability and protecting the environment of Loch Long was an important consideration for the project team. The use of capture blankets prevented material from entering the water when the old jetty was demolished. All jetty demolition waste was transported on barges offsite to recycling facilities on the Clyde to minimise disruption to the public and will be reused for construction. To avoid the need to lay new electric cables through the water, the new navigation aids are solar powered.

There were concerns about the possible impact of noisy piling works on marine mammals, so two observers used underwater listening devices, along with visual inspections, to make sure no marine mammals were in the area before work began. If any were located, work was stopped to give them time to move away.

Craig MacDonald, DIO’s Project Manager, said: "It’s been such a pleasure to work on such a nationally-important and dynamic project. The project has faced numerous challenges, but they have been overcome with good teamwork, communication and collaboration. It’s great to see this vitally important facility now in full operation."

John Cox, managing director, VolkerStevin said: "We are very proud to have played a key role in the successful delivery of all three phases of the Queen Elizabeth Class Aircraft Carrier infrastructure upgrade programme. The completion of this final phase, is testament to the hard work and commitment of the entire team, and demonstrates the benefits of a strong collaborative approach in the delivery of complex critical infrastructure projects."

Justin Goldberg, Jacobs’ Vice President for Defence & Security, said: "As Principal Service Provider, we managed the contract on behalf of DIO as part of a dedicated team with the vision and drive to keep this project moving forward. Through early contractor engagement and close collaborative working, we were able to deliver within budget and programme constraints, providing the Royal Navy with an important facility for years to come while ensuring sustainability and protection of the environment. We are now applying best practice from this exemplar project to other maritime work."

As a critical national infrastructure project, work continued through the pandemic with all necessary precautions taken and guidance followed to keep everyone safe.

The jetty was handed over to Defence Equipment and Support, who will operate it. The Glen Mallan Northern Ammunition Jetty is the third and final jetty refurbishment to support the nationally critical £7-billion Queen Elizabeth Class (QEC) Aircraft Carrier programme.
 

 

Other Stories
Advertisement
Latest News

Jaltek selected to join SiG

Luton based electronics manufacturing company Jaltek has been accepted on to the UK's award winning aerospace transformation programme, Sharing in Growth (SiG).

NATS in holding pattern for increasing UK air traffic levels

Air traffic figures for 2021 show the UK aviation industry is still struggling to recover from the pandemic - as numbers changed little from 2020 and remained volatile - with the UK's National Air Traffic Services (NATS) ready to respond

Airbus C295 FTB2 makes maiden flight

The Airbus C295 Flight Test Bed 2 (FTB2) technology demonstrator of Clean Sky 2, has successfully performed its maiden flight from the Final Assembly Line in Seville.

EasyJet receives IATA IEnvA Stage 1 accreditation for EMS

As the first non-IATA member to participate in the IEnvA accreditation process, easyJet has become the only Low-Cost Carrier operating in the UK to receive an IEnvA Stage 1 verified Environmental Management System (EMS)

BA and American Airlines to co-locate at enhanced JFK T8

American Airlines and British Airways have revealed further details regarding plans to co-locate operations at John F. Kennedy International Airport’s (JFK) Terminal 8 beginning 1st December 2022.

UK-built Solar Orbiter catches a second comet by the tail

The UK-built Solar Orbiter spacecraft has flown through the tail of a comet for the second time in its mission so far, Comet Leonard, collecting valuable scientific data on the particles and magnetic field present in its tail.

ODU SK2401311222
See us at