NAO: The UK’s Defence Investment Plan was still £1.2bn over budget when published
The Ministry of Defence closed most of a £28.8 billion gap in its four-year spending plans through extra Treasury funding and reductions to planned military activity. Even so, the Defence Investment Plan was forecast to cost £1.2 billion more than the MoD had available when it was published in June, according to the National Audit Office (NAO).
The Armed Forces will receive £11.3 billion less for readiness over the four years to 2029–30 than they initially proposed to deliver the Strategic Defence Review. Of that difference, £8.6 billion relates to training and other military activity. The MoD accepted that some of its spending decisions would leave gaps in capability or reduce readiness.
How a £1.4bn gap became £28.8bn
When the government published the Strategic Defence Review in June 2025, the MoD estimated that its plans would cost £1.4 billion more than its four-year budget.
A more detailed costing exercise over the summer produced a substantially different answer. By November, the MoD, Treasury and Cabinet Office agreed that existing programmes and commitments would cost £314.9 billion, putting them £28.8 billion over budget.

By February 2026, officials had brought the gap down to £18.3 billion and concluded that the remaining decisions needed the Prime Minister and Chancellor. In June, the Treasury agreed an extra £11.6 billion in cash funding alongside other measures worth £3.4 billion.
The final investment plan was published on 30 June, six months later than intended, with a revised four-year budget of £297.7 billion.
The MoD considers that settlement broadly affordable through 2029–30. However, its budget for military activity will rise only in line with economy-wide inflation. Fuel and equipment maintenance costs are rising faster, putting pressure on how much training and other activity the services can sustain.
The plan also assumes £10.7 billion in efficiency savings over four years. At the time of the audit, the MoD had well-developed plans for £2.4 billion of them.
MoD assumes a fifth of project spending will slip
For defence suppliers, one of the most consequential assumptions concerns when orders will translate into work. The MoD generally expects around 8% to 10% of project costs in a balanced programme to fall later than scheduled. In drawing up the investment plan, it assumed about 20% of project spending would move into later years.
The MoD’s procurement officials identified one reason for that uncertainty. The department had been unable to engage with industry while it developed the plan, leaving suppliers needing time to assess the programme and prepare for it.
On the government side, the National Armaments Director Group reported a staffing shortfall of around 18% in June. It judged that it needed to bring that within 10% to manage the workload.

Beyond 2030, the timing of the UK’s promised increase in defence spending matters to companies deciding when to recruit skilled workers or expand production. The Treasury has said it will set out how the UK will reach its NATO commitment of 3.5% of GDP on defence by 2035 in next year’s Spending Review.
The NAO warned that without a clearer picture of when demand will rise, the MoD and its suppliers risk reaching the point when the money is available without the people or capacity to deliver.