London City Airport completes key airfield infrastructure projects

London City Airport has completed key improvements to its airfield infrastructure as part of the City Airport Development Programme (CADP), including the construction of a full-length parallel taxiway and eight new stands capable of handling larger and more fuel-efficient aircraft.

Image courtesy London City Airport

The airfield infrastructure at London City Airport has been transformed in the past three years, with the construction of a new 70,000m2 concrete deck to house the parallel taxiway and aircraft stands.

The deck was created by drilling 1,000 piles of concrete 20m below the bed of the King George V Dock - one of the most challenging and complex civil engineering and inland marine construction projects in Western Europe. The deck is equivalent to the size of 10 football pitches and its completion required the work of 45 contractors and took over 1.2 million hours. Not even the discovery of a World War II bomb in the dock bed hindered progress for long.

Advertisement
ODU RT

The parallel taxiway is now operational, maximising the potential of the airport’s runway and providing the ability to allow 45 aircraft movements per hour when demand returns. In addition, the airport now possesses eight new aircraft stands capable of accommodating the next generation of cleaner, more sustainable aircraft such as the Airbus A220 and Embraer E2-190.

Passengers will also benefit from improved facilities in the terminal, including a larger immigration facility with 10 new e-gates and a new outbound baggage facility. Once complete, this facility will be able to process 2,400 bags per hour and feature the latest security screening technology.

A digital Air Traffic Control Tower has also been constructed, with plans for it to be operational early next year - a global first for a commercial airport of this size, demonstrating the airport’s ongoing commitment to technological innovation.

London City Airport Chief Executive, Robert Sinclair, said: “The completion of this vital new airfield infrastructure is a major milestone for the airport and will help us to return to growth, welcome new airlines and aircraft and once again connect London to the rest of the UK and to the world.

“The parallel taxiway and aircraft stands are key components of how we plan to build a better and more sustainable airport in the future, providing our airlines with the potential to bring more cleaner, quieter next generation aircraft to the airport in the coming years.

“The new facilities for immigration and baggage will also enhance our industry-leading passenger proposition, ensuring that London City Airport continues to provide the quickest and most convenient airport experience in London”.

Advertisement
ODU RT

The airport worked with contractors to ensure that industry-leading sustainability practices were at the heart of the three-year construction project. For the concrete deck, a controlled off-site environment for cement replacement was used, which reduced waste and saved 3,105 tonnes of carbon emissions.

The project also supported enhanced biodiversity by transporting 29,000 tonnes of soil from marine piling works to Rainham Marshes, a designated local Site of Specific Scientific Interest. This was used to restore the silt lagoon and create a new habitat for bird wildlife. The use of river barges minimised noise and air pollution and equated to 1,622 lorry journeys being removed - saving 103.4 tonnes of carbon emissions.

Innovative cleaner fuel using hydrotreated vegetable oil was also deployed to power temporary generators, further reducing carbon emissions. The CADP project’s commitment to sustainable construction was recognised with the Green Apple award for Environmental Best Practice in November 2019.

The second phase of the City Airport Development Programme, including construction of the terminal extension and new east pier, were temporarily paused in summer 2020 due to the short-term impact of Covid-19. These projects remain part of the airport’s future plans, and with the foundations now in place, will be progressed as demand recovers in the UK aviation market. 

 

Advertisement
Hexagon leaderboard
RIAT 2026 cancelled

Aerospace Defence Security Events

RIAT 2026 cancelled

22 May 2026

This year’s Royal International Air Tattoo (RIAT) will now not be taking place, cancelled due to issues regarding access to the event - at RAF Fairford in Gloucestershire - amid concerns over conflict in the Middle East.

ADS appoints Andy Williams Director of ADS Scotland

Aerospace Defence Security Space

ADS appoints Andy Williams Director of ADS Scotland

22 May 2026

ADS, the trade association for the aerospace, defence, security and space industries, has announced the appointment of Andy Williams as Scotland Director.

King’s College London and Cranfield University propose merger

Aerospace Defence Security Space

King’s College London and Cranfield University propose merger

22 May 2026

King’s College London and Cranfield University have announced that the two universities have signed an agreement as the first step towards a merger, with the aim of bringing the two institutions together from August 2027, which will support UK national capability and resilience.

BAE Systems

Aerospace Defence

BAE Systems' Iain Minton to chair new manufacturing and tech coalition

21 May 2026

BAE Systems' tech specialist Iain Minton has been appointed to chair a new coalition of manufacturing and industrial technology experts helping SMEs tackle the challenges and opportunities created by AI, automation and digital transformation.

Advertisement
ODU RT
Ontic appoints Jean-Christophe Gallagher as CEO

Aerospace

Ontic appoints Jean-Christophe Gallagher as CEO

21 May 2026

Ontic has announced the appointment of Jean-Christophe (JC) Gallagher as Chief Executive Officer (CEO), as the company builds on a sustained period of strong growth.

Muirhead Avionics appointed ARC for selected IA products

Aerospace

Muirhead Avionics appointed ARC for selected IA products

19 May 2026

AMETEK MRO's Muirhead Avionics, announced today that it has entered into a long term agreement with Innovative Aerosystems (IA) to become an Authorised Repair Centre (ARC) for selected legacy avionics products formerly developed under Honeywell product lines and now fully supported by IA.

Advertisement
ODU RT
Advertisement
FIA2026 animated banner