London City Airport completes key airfield infrastructure projects

London City Airport has completed key improvements to its airfield infrastructure as part of the City Airport Development Programme (CADP), including the construction of a full-length parallel taxiway and eight new stands capable of handling larger and more fuel-efficient aircraft.

Image courtesy London City Airport

The airfield infrastructure at London City Airport has been transformed in the past three years, with the construction of a new 70,000m2 concrete deck to house the parallel taxiway and aircraft stands.

The deck was created by drilling 1,000 piles of concrete 20m below the bed of the King George V Dock - one of the most challenging and complex civil engineering and inland marine construction projects in Western Europe. The deck is equivalent to the size of 10 football pitches and its completion required the work of 45 contractors and took over 1.2 million hours. Not even the discovery of a World War II bomb in the dock bed hindered progress for long.

Advertisement
ODU RT

The parallel taxiway is now operational, maximising the potential of the airport’s runway and providing the ability to allow 45 aircraft movements per hour when demand returns. In addition, the airport now possesses eight new aircraft stands capable of accommodating the next generation of cleaner, more sustainable aircraft such as the Airbus A220 and Embraer E2-190.

Passengers will also benefit from improved facilities in the terminal, including a larger immigration facility with 10 new e-gates and a new outbound baggage facility. Once complete, this facility will be able to process 2,400 bags per hour and feature the latest security screening technology.

A digital Air Traffic Control Tower has also been constructed, with plans for it to be operational early next year - a global first for a commercial airport of this size, demonstrating the airport’s ongoing commitment to technological innovation.

London City Airport Chief Executive, Robert Sinclair, said: “The completion of this vital new airfield infrastructure is a major milestone for the airport and will help us to return to growth, welcome new airlines and aircraft and once again connect London to the rest of the UK and to the world.

“The parallel taxiway and aircraft stands are key components of how we plan to build a better and more sustainable airport in the future, providing our airlines with the potential to bring more cleaner, quieter next generation aircraft to the airport in the coming years.

“The new facilities for immigration and baggage will also enhance our industry-leading passenger proposition, ensuring that London City Airport continues to provide the quickest and most convenient airport experience in London”.

Advertisement
ODU RT

The airport worked with contractors to ensure that industry-leading sustainability practices were at the heart of the three-year construction project. For the concrete deck, a controlled off-site environment for cement replacement was used, which reduced waste and saved 3,105 tonnes of carbon emissions.

The project also supported enhanced biodiversity by transporting 29,000 tonnes of soil from marine piling works to Rainham Marshes, a designated local Site of Specific Scientific Interest. This was used to restore the silt lagoon and create a new habitat for bird wildlife. The use of river barges minimised noise and air pollution and equated to 1,622 lorry journeys being removed - saving 103.4 tonnes of carbon emissions.

Innovative cleaner fuel using hydrotreated vegetable oil was also deployed to power temporary generators, further reducing carbon emissions. The CADP project’s commitment to sustainable construction was recognised with the Green Apple award for Environmental Best Practice in November 2019.

The second phase of the City Airport Development Programme, including construction of the terminal extension and new east pier, were temporarily paused in summer 2020 due to the short-term impact of Covid-19. These projects remain part of the airport’s future plans, and with the foundations now in place, will be progressed as demand recovers in the UK aviation market. 

 

Advertisement
FIA2026 animated banner
IFS launches IFS Zero

Aerospace Defence

IFS launches IFS Zero

10 June 2026

IFS has launched IFS Zero, an agentic AI Emissions Operating System designed for asset-intensive industries, such as aerospace and defence, where organisations face pressure to improve emissions reporting and supply chain transparency, with Scope 3 compliance now a contractual requirement.

Smith Detection

Aerospace Security

Smith Detection's SDX 10080 SCT receives UK DfT approval

10 June 2026

Smiths Detection announced today that its SDX 10080 SCT has received UK Department for Transport (DfT) approval for deployment across UK airports and cargo operators for hold baggage and air cargo screening.

Aston University secures £3.9m to boost aerospace and cybersecurity skills

Aerospace Security

Aston University secures £3.9m to boost aerospace and cybersecurity skills

10 June 2026

Aston University has secured almost £4 million in new funding to improve the UK’s aerospace engineering and cybersecurity skills.

Marshall Aerospace completes initial flight model for Horizon Aircraft’s Cavorite X7

Aerospace

Marshall Aerospace completes initial flight model for Horizon Aircraft’s Cavorite X7

10 June 2026

Marshall Aerospace has successfully completed a flight dynamics and control model to support Horizon Aircraft’s Cavorite X7, a revolutionary dual-use hybrid-electric vertical take-off and landing (VTOL) aircraft currently in prototype development.

Advertisement
ODU RT
NATS invests in carbon removals with CUR8

Aerospace

NATS invests in carbon removals with CUR8

9 June 2026

NATS has committed £500k to carbon removals through carbon removals intelligence provider CUR8, contributing to an initiative led by the UK Sustainable Aviation coalition, to stimulate the carbon removals market as part of a £2 million Advance Market Signal.

HutanBio partners with Wakud on scalable SAF feedstocks

Aerospace

HutanBio partners with Wakud on scalable SAF feedstocks

9 June 2026

Cambridge biotechnology company HutanBio, which is developing algae-derived oils for sustainable aviation fuel (SAF), has signed its first commercial offtake Memorandum of Understanding (MoU) with Oman's Wakud International, as the aviation industry searches for new feedstock sources capable of supporting future SAF demand.

Advertisement
ODU RT
Advertisement
General Atomics LB