Stansted shifts to daytime runway maintenance

London Stansted’s engineering team is using the unprecedented grounding of aircraft across the globe as a unique opportunity to move planned overnight runway maintenance works to daytime hours.


Courtesy MAG

Stansted’s 3,048 foot runway undergoes full re-surfacing work every 10 to 15 years but, as with other busy airports, regular heavy maintenance also takes place twice a year, overnight at weekends in the spring and autumn to minimise disruption to flights.

While the airport remains open for business with a limited number of commercial flights still operating, as well as a busy cargo operation that continues to bring vital supplies into the UK, the current reduction in flights has enabled the engineering and airfield operational teams to close the runway during part of the day. This change creates an extended period of time for specialist contractors to safely access the runway and makes it easier to carry out technical work in daylight hours rather than at night.

Advertisement
ODU RT

The runway works are taking place on weekdays between 14th April to 24th April.

The project is being managed by Stansted’s Engineering Maintenance team and delivered by Marriott Civils, with up to 200 contractors and engineers plus 100 vehicles and items of machinery tasked with laying the 1,000 tonnes of asphalt necessary to complete the work.

At the same time, 3,600 airfield lights are being upgraded with energy efficient, high performance LED lamps, similar to those already installed on the runway, that are crucial in the safe operation of aircraft in low visibility conditions. The new low energy LED variants will reduce power output from airfield lights by around 70%, helping drive down operating costs and cutting emissions.

London Stansted’s Asset Maintenance Services Director, Kathy Morrisey, said: “We all recognise this is an extremely difficult and challenging time for the whole country, and here at the airport it is no different following the dramatic and unprecedented reduction in flights.

“The situation has however given us the unique opportunity to access the runway during the day when usually we would have hundreds of aircraft landing or taking off.

Advertisement
Leonardo RT

“This means that rather than a maximum of three and a half hours a night over the weekend, the team will have up to six hours each weekday to complete complex maintenance work without the same time pressures and challenges of working overnight.

“The runway is obviously a key asset for the airport, and it’s critical it is maintained to the highest standard, so while we are in a situation none of us would wish to be in, we are using this as an opportunity to carry out essential work to ensure the airport is able to return to normal as quickly as possible once the current restrictions are lifted.”


 

Advertisement
PTC PTC
IATA sees rising passenger and cargo growth in May

Aerospace

IATA sees rising passenger and cargo growth in May

30 June 2025

The International Air Transport Association (IATA) released data for May 2025 that revealed global passenger demand was up by 5% and global air cargo demand grew by 2.2%.

ECT Aviation acquires its first Britten-Norman BN2T-4S Islander

Aerospace

ECT Aviation acquires its first Britten-Norman BN2T-4S Islander

30 June 2025

Republic of Ireland based ECT Aviation has acquired its first Britten-Norman BN2T-4S Islander aircraft, expanding its operations into dedicated cargo services between Europe and North Africa.

IBA predicts more large orders of aircraft in 2025

Aerospace

IBA predicts more large orders of aircraft in 2025

30 June 2025

Despite the Air India tragedy and a range of economic and political factors impacting the aviation industry, reflected by a subdued level of orders at this year's Paris Air Show, aviation intelligence and advisory company IBA predicts that a range of major airlines are set to place additional aircraft orders.

Qantas takes delivery of its first A321XLR

Aerospace

Qantas takes delivery of its first A321XLR

30 June 2025

Australia's Qantas Airways is set to become the Asia-Pacific launch operator of the latest generation single aisle A321XLR following the delivery of its first aircraft from the Airbus assembly line in Finkenwerder, Hamburg.

Advertisement
DSEI 2025
Syensqo and Terma strengthen partnership

Aerospace Defence Security

Syensqo and Terma strengthen partnership

30 June 2025

Advanced materials specialist Syensqo and Terma, provider of mission-critical solutions in aerospace, defence and security, have signed a strategic collaboration agreement to develop joint initiatives in composites for next-generation aerospace and defence applications.

Windracers establishes operational hub in Malawi

Aerospace Security

Windracers establishes operational hub in Malawi

27 June 2025

Windracers, the UK-based designer, manufacturer and operator of Windracers ULTRA - an autonomous heavy-lift cargo aircraft - has begun establishing an operational base at Kasungu Airfield in Malawi.

Advertisement
Gulfstream RT